Introduction:​
-
Constructed bridge to connect rural area with urban area, which is located in another the other side of the river.
-
Generated Project Management Plan.
Details:
-
Created Gantt chart based on WBS, WBS dictionary and project scope statement.
After generated the project scope, WBS (Fig. 6-2) was made to breakdown the project into small work packages. The duration and necessary resources (Fig. 6-5) were assumed in order to get the final project cost (Fig.6-6). The critical path in read was very clear from the Gantt chart (Fig. 6-1) that helped us control the project duration which was 422 days within 2 years we expected.
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
(Fig.6-1 Gantt chart)
​
​
​
​
​
​
​
​
​
​
​
​
​
(Fig.6-2 WBS)
​
2. Generated Project baseline with milestone and summary task
The project baseline gave us a straight view about the milestone during our project construction state.
​
​
​
(Fig.6-3 Project baseline)
​
3. Risk analysis
Through brainstorming and reviewed the historical records, Risk Severity Matrix was created to maintain the risk impact to our project. In the end, we came up with the risk management plan.
​
​
​
​
​
​
​
​
​
​
​
​
​
​
(Fig.6-4 Risk matrix)
​
4. Cost estimate
​
​
​
​
​
​
​
​
​
​
(Fig.6-5 Resource Sheet)
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
(Fig.6-6 Cost Estimate)
​
​
Managed a bridge project in Tucson
(ENTR-557, 2016 Fall)